How long does a rooflight replacement take?
A straightforward like for like swap is a day on the roof. What makes a replacement feel longer is everything either side of that: the lead time on the unit before anybody arrives, and the plastering and decorating afterwards. The roof work is the short part, and the room is usually finished a week or so after the roofers have gone.
Before anybody arrives
The survey and the order.
The kerb or the opening is measured, the unit is specified, and it is manufactured to that size, which is a lead time rather than a delay in anybody’s diary.
Why the unit is made rather than stocked
Because a replacement is measured. Standard sizes exist and an existing opening rarely matches one exactly, so most replacements are made to the measured kerb.
What is measured is on can a rooflight be replaced in the same opening.
Access first
Sometimes a separate visit at each end.
A tower goes up and comes down on the day. A scaffold is erected before and struck after, which adds days at each end of the programme rather than to the work.
Protecting the room
The first hour on the day. Furniture is moved and covered, the floor is sheeted, and the area beneath the opening is cleared, because a replacement usually happens in a finished room.
Taking the old unit out
Quicker than it looks. The covering is lifted back from the perimeter, the fixings are released and the old rooflight is lifted off, which on a modest unit is an hour or two.
Assessing what is underneath
The point where a programme can change.
With the unit off, the kerb, the trimming and the covering are inspected, and if the timber is wet, the job becomes a longer one.
What that involves is on what happens if the timber underneath has rotted.
Repairs to the kerb
Half a day to a day where they are needed.
Rebuilding an upstand, insulating one properly or squaring one up is carpentry, and it is worth doing rather than working round.

Setting the new unit
An hour or two on a straightforward job.
The frame is bedded and fixed to the kerb, checked for level and square, and the covering is dressed up and terminated under it.
Weathering it
The part that decides the result. Dressing the covering up the kerb and terminating it correctly is where the time is properly spent, and it is not a stage to rush at the end of a day.
On a pitched roof
Similar, with the courses instead of the covering.
The tiles or slates come off around the opening, the flashing kit goes on, and the courses go back so they run true either side.
What the covering adds
Hours on an old roof.
Hand made clay or natural slate has to be set out rather than simply put back, and breakages have to be matched from a similar source.
Why is on flashing an irregular gauge.
Making good the reveal
A separate trade, afterwards.
Boarding and insulating the reveal is part of the installation. Skimming, drying and decorating follows, and that is days rather than hours.
Why the plaster decides the finish
Because it has to dry.
Fresh plaster wants time before it is painted, longer in cold weather, and that interval is usually what stands between the roof work finishing and the room being done.
Several rooflights and skylights at once
Much less than the sum.
Access, protection and setting out happen once, so three replacements on one visit is a longer day or two rather than three separate jobs.

Where the roof is being recovered
The replacement disappears into it.
On a roof that is coming off anyway, the rooflight is part of the covering programme rather than a job of its own.
A glass only replacement
Much shorter.
Where only the sealed unit has failed and the glass is beaded, the pane is changed in a morning with no covering disturbed at all.
That route is on can just the glass be replaced.
Where an inspection is involved
Arranged rather than waited for.
Where the work is notifiable, the visit is booked into the programme, and on a straightforward replacement it rarely adds a day.
What applies is on does replacing a rooflight need building regulations.
Weather
Matters on one day rather than all of them.
The roof is open for part of the day the unit is swapped, and that day is moved rather than pushed through on a forecast that will not hold.
Wind
The reason a dry day still gets postponed.
A sealed unit is handled above head height on a roof, and a gusty day makes that unsafe whether or not it is raining.
Is the roof ever left open
No, and it is worth saying.
The work is sequenced so the opening is covered and weathertight at the end of every day, whatever stage it has reached.
What is asked of the household
Clearing and access.
The area under the rooflight cleared, access to the room, and somewhere to stand the access equipment is generally the whole of it.
What we give you on a replacement
We give a programme rather than a figure, and we say when the plastering will be, because the question people actually have is when their kitchen will be usable rather than how long the roof takes.
The whole picture is on the replacing a failed or misted rooflight page.
Thinking about this job? We survey across Worthing, West Sussex and the South Downs and give you a fixed price before any work starts, with a 10-year workmanship guarantee.